BeltanaMineSurfaceInfrastructureMineOperating.jpg (76337 bytes) BeltanaMineSurfaceInfrastructureStackout.jpg (73587 bytes) BeltanaMineSurfaceInfrastructureBuildingAreaArrgt01.jpg (49755 bytes) BeltanaMineSurfaceInfrastructureBuildingAreaArrgt02.jpg (110824 bytes) BeltanaMineSurfaceInfrastructureBuildingAreaArrgt03.jpg (68735 bytes) BeltanaMineSurfaceInfrastructureBuildingAreaArrgt04.jpg (106214 bytes) BeltanaMineSurfaceInfrastructureBuildingElectIncoming.jpg (73727 bytes) BeltanaMineSurfaceInfrastructureEntryPortal.jpg (82196 bytes) BeltanaMineSurfaceInfrastructureAccessRoad01.jpg (65490 bytes) BeltanaMineSurfaceInfrastructureAccessRoad02.jpg (58958 bytes) BeltanaMineSurfaceInfrastructureAccessRoad03.jpg (55284 bytes) BeltanaMineSurfaceInfrastructureAccessRoad04.jpg (104920 bytes) BeltanaMineSurfaceInfrastructureRoadworks.jpg (61430 bytes) BeltanaMineSurfaceInfrastructureAirSystem.jpg (78141 bytes) BeltanaMineSurfaceInfrastructureHighwallServicesDropper.jpg (83552 bytes) BeltanaMineSurfaceInfrastructureHighwallWaterAndElectIncoming.jpg (80148 bytes) BeltanaMineSurfaceInfrastructurePond.jpg (49630 bytes)

This project was undertaken on behalf of Peter Eason Survey for Roche Mining. Calsun provided the total project management of the surface infrastructure of this new mining operation to go underground at the final highwall of South Bulga's Opencut mine. This included engineering and construction management for the new facilities.

$2.1M Beltana Mine Surface Infrastructure Installation
for Roche Mining (Project Management)

Key Benefits

  • Commissioned 1 day ahead of very tight schedule.
  • Project achieved under budget.
  • Embraced additional tasks to recover time lost by others to let mining start on schedule.

 